teamed with Emery Sapp and Sons to do a design-build redo of 79th
Street between Pflumm and Lackman — right in front of the school. Despite a
construction schedule slowed by rain, the ESS/GBA team was able to have 79th
Street open and drivable last week when the students had a kick-off playdate
with a firetruck in the school parking lot (above).
Roadwork is expected
to be complete Sept. 27th, on the project, which began immediately
with selection by the city Feb. 20th. GBA submitted preliminary
plans for the first phase of construction on April 11 and final plans on that
phase April 24th.
Great project! Wish the weather and a couple other aspects had been more cooperative so there could be an even speedier completion. Bottom line, though, is you want to end with a high quality job. GBA and ESS make an excellent team! Thank you! Dyanne Bean